You know how it goes. You get a call/mail/text with something along the lines of “I need to know all the details of customer orders placed on Tuesday 7th by customers based in Botswana – and I need it ASAP, by end of play today at the latest”. So you skip lunch, drop that task you have been trying to get around to doing all week and work out how to resolve the issue that has just been dropped on you. It takes a lot of effort and you finally get it sorted out around an hour after you told your girlfriend/boyfriend/cat you would be leaving the office that day – and mail it off to the requestor. You might even call them to let them know it is done, but oddly they don’t answer.

Next day, you see the guy who wanted this urgent request and ask if it was what they wanted “Oh, I have not looked at it yet – but thanks for doing it.”

NO! “Thanks” does not work in this situation. I’d have more respect for this guy if he laughed at me and said “got you again, sucker”. Many of you know what I mean don’t you – if you are in a support-type-role, this can be a big part of your life.

I had a job years back that seemed to consist 90% of such tasks. I was the development DBA team leader responsible for testing, validating and promoting code to production. Everyone’s changes were Urgency Level 1, to be done as an emergency release and many could not be put in place until after 5pm. I’d be sat there at 18:30 in a massive but virtually empty office, applying changes along with one or two of my guys. Everyone else had gone home. This was not once or twice a month, it was 4 or 5 times a week. What are you to do?

Well, I came up with one tactic that seemed to work pretty well.

Anyone who asked for an emergency change had to be there, on site, available when the change was done.
There were of course cries of protest and people stated it was ridiculous that they had to be there, they were not needed, the change had been tested thoroughly {oh how I laughed at that – a thoroughly tested “emergency” change huh?}. No, I replied, you had to be there in case it went wrong as it’s your system, your data and, frankly, your emergency. If it is not urgent enough for you – the guy wanting it to be done – to be inconvenienced, well it sure as hell is not urgent enough to inconvenience me. “You can call if there are problems” – What, after you have escaped the locality? Maybe turned off your phone? And if I get you , I have to wait for you to come back in? No no no. Urgent emergency now equates to presence in office. After all, I’ll be there.

I stuck to my rule. If the requester could not be bothered to stay, I downgraded the request to “Planned” and put it through the CAB process. If the requester dumped on one of their team and made them stay, I mentally marked them half a point down and factored it in next emergency.

The change was remarkable. I was no longer in the office on my own every evening. I was not there with someone else either. I was simply not there as, when you made the emergency a little bit inconvenient to the requester, it magically stopped being an emergency.

There was another change. Less cock-ups. Seeing as these changes now went through the CAB process and slightly more testing {like, some testing} the duff changes were more likely to be detected before they caused damage. My bosses went from regarding me as “not a team player” to “Not a team player – but we kind of get your point now”.

So my advice is, if someone wants to try and make something your emergency, find some way of making sure it remains inconvenient to them. If they are willing to put up with the inconvenience, then it is a real emergency and you need to crack on with it.

Friday Philosophy – Team Ice-Cream and Telling Offs September 30, 2011

Posted by mwidlake in Friday Philosophy, Management.
Tags: ,
5 comments

If you manage people, it helps if they don’t dislike you. Sadly, this can be the default starting opinion for some people who have never been managers (we all know someone who “has never had a decent manager, they are all bloody idiots”). Frozen dairy products might be a route to easing this situation.

I mention this as we in the UK are having an unusually warm start to autumn, an Indian Summer as we call it. I used to work in a place that had an on-site cafe and a nice area outside to sit. If the weather was warm and I knew my team was not facing some crisis, I would occasionally pop my head around the door and announce “Team Ice-Cream!”. Anyone who wished could come down with me and I would buy them an ice-cream of their choice and we would sit out in the sun for 15 minutes and talk rubbish.

I’ve done similar in other situations. Taking the guys to the pub is the obvious one and it usually is appreciated, but in some ways it is less successful. I think this is because people will come to the pub because they want a pint and will put up with any idiot willing to provide a pint of Fosters (why is it so many of the “all managers are idiots” brigade drink some brand of nasty lager?). People will come for a tea/coffee or an ice-cream only if they are at least ambivalent to the provider. If you really dislike someone, who cares about an ice-cream? The serious malcontents will stay away and this helps identify people who really are not happy with you {so you can beat them mercilessly of course – or, if you’ve progressed beyond the school-yard, put some thought into why they are unhappy and what to do about it}.

By the way, this is very different to everyone going to the pub/restaurant in the evening and spending hours telling people what “you really think” and trying to impress Jessica the new trainee/intern. Such team building events generally need much more planning.

It’s a cheap bribe, should you resort to such shallow tactics to make people like you? Well, it’s only a cheap bribe as I said above. The trick to it is that it has to be {almost} spontaneous, such that the team are not expecting it, and not all the time. I’m not sure the teams I have done this for have always appreciated that I made special effort to do this either after a hard period of work or when there had been some malcontent within the team (people fall out, it impacts the rest of the team). The way I look at it, it also has to be a team thing and not an individual thing as the sitting around talking rubbish is a key part to the team being a team. Even if it is just over a cup of nasty coffee in the basement – that particular company’s canteen was not the best.

Oh, I should mention that I have access to a wife that makes wonderful cakes. Left-over cake is a brilliant “team ice-cream” substitute, it is both “cheap” so not a bribe but also appreciated as someone put effort in. My wife in this case. I Never claim I made the cake. well, not often.

TeddyBear Picnic Cake

That’s the carrot. What about the stick? When it comes down to it, you are there to guide the team and the individuals in it and get the best you can out of them. Not being disliked is important but you are not there to be their friend either. If someone transgresses you need to correct them.

In my opinion one of the very worst things a manager can do is dress down a member of their staff in public. That is not correcting them, that is either an attempt to humiliate them or an attempt by the boss to scape-goat the blame to a subordinate. Neither is morally correct and both are highly likely to engender considerable dislike or even hatred.

I distinctly remember one situation where I was in a team meeting and the boss’s managers came in and wanted to know why a recent change had gone so badly wrong. The manager’s response was immediate, he picked one of the team and said something like “It was him, he didn’t test the change properly”. It was so obvious that the sub-text was “it was not my fault”. In reality the sacrificed staff member was not at fault but the boss sure as heck was. A manager gets paid more as a boss and part of the reason is that you take both the credit and the blame for your team’s efforts. This action by that boss did not make us scared of failing and thus work harder, it made us distrust the man and demoralised us.

Sadly it is something I’ve seen a lot over the years and never by what I would call a good manager. I just don’t understand why these people think a public dressing down is going to inspire the target or the audience to work more effectively.

If I’m in the situation where, in a meeting or discussion, it becomes obvious one of my guys has screwed up we discuss how to sort it out as a team. Then after the meeting, the transgressor and I have a private conversation. This has several benefits:

  • I am not publicly humiliating them or scoring points in front of a crowd.
  • Neither of us is playing to the crowd and so are more likely to be honest.
  • Things can be said that stay private. I’ve had team members mess things up because they have more important issues on their mind that they are uncomfortable with the team knowing about. I’ve had to tell a guy this is chance #last and the next step is disciplinary.
  • This never happens, but there is a very small theoretical chance I could have misunderstood and, in fact, it’s my fault. You look a right idiot if you attempt to dress someone down in public and it turns out to be you.

As I said, that last point has never happened to me {yes, this is an outrageous lie :-) }. I’ve experienced that last point from the other side as well. In a large meeting I had a board member pushing me as to why we had not finished a project on the date I promised. I kept giving vague answers about “other things coming up” and it would be done by a new, given date. She would not let it go though so eventually I had to say “It is late because you told me to do other stuff as top priority, I raised this project and you told me to delay it. So it is late because you changed the priorities. That would make it your responsibility.” She was very angry but it had been her choice to do this publicly.

All this boils down to – Reward the team in public. Chastise the individual in private.

In Defense of Agile Development (and Their Ilk) September 21, 2011

Posted by mwidlake in development, Management.
Tags: , , , ,
10 comments

In my previous post I asked the question “why doesn’t Agile work?”. I’m not sure the nuance of the question came over correctly.

I’d just like to highlight that the question I asked was “Why does agile not work”. It was not “Why is Agile rubbish“. I’ve said a few times in the past couple of weeks that I like the ideology of Agile and I am (and have been for years and years) a strong proponent of prototyping, cyclic development, test driven design and many other things that are part of the Agile or XP methodologies.

That distinction in the title is a really important distinction and one I’d hoped I’d made clear in my post. Looking back at my post though, I think it is clear I failed :-(. I highlighted reasons why I think Agile does not work and in my head I was thinking “if we avoid these, Agile could work” – but when you write something down it does not matter what is in your head if it does not reach the paper.

I’m actually frustrated that in the last few years I have not seen Agile really succeed and also that this must be the normal situation, going on the response you get when the topic of Agile comes up with fellow technicians and comments on my own blog.

However, on that post about Agile two people who’s opinion I deeply respect came back at me to say “Agile does work!”. Cary Millsap, who many of you will have heard of as the “Method R” guy and the person behind Oracle Flexible Architecture. And Mike Cox, who most of you won’t have heard of but Mike taught me a lot about sensible development back in the 90′s. He’s one of the best developers I have ever had the pleasure of working with and I know he has had great success with Agile and RED. I’m not sure if they read my post as “Agile is Rubbish” or they are, like me, simply frustrated that it can work but so often does not.

So I’ve been thinking about this a lot this weekend and I was helped by Cary’s paper on the topic that he mentioned in his comment. I’d highly recommend downloading it as it is an excellent description of not only why Agile can help but describes how and some of the pitfalls {I’d started my own post on that, but go read Cary’s}. I should add, you can see Cary present his case for Agile at the UKOUG conference this year.

So where does this bring me to? Well, I think “Is Agile good or bad” has become almost an “IT religion” topic, people love it or loath it and it is based on what they have seen of the methodology in real life. No, that’s wrong, it is based on what they have seen that has been labelled with that methodology in real life. Or worse, it is based on anecdotal opinion of those around them. The thing is, if you look at what XP is supposed to consist of or what Agile Programming is supposed to consist of, most of us would agree that a great deal of it makes sense in many situations. I’d disagree with some of the details in Cary’s paper but overall I’m in strong agreement. Sadly, What Agile and XP is supposed to be is not well matched by what you see on the ground in most cases. So even if these methodologies are right for the situation, what has been implemented is not the methodology but probably more a slap-dash process that simply jettisons documentation, design and proper testing. This whole thread sprung from my lamenting the demise of database design and several of the comments highlighted that the introduction of Agile seemed to equate, at least in part, with the demise of design. As MIke and Cary say, and as I think anyone who has successfully utilized Agile would say, Design is an integral part of Agile and XP methodology.

Agile can and does work. But many things can and do work, such as taking regular exercise to keep healthy or regularly maintaining your house to keep it weathertight. Like Agile, both take effort but the overall benefit is greater than the cost. And like Agile, do it wrong and you can make things worse. If your window frames are starting to rot and you just slap a new layer of top-coat on them all you will do is seal in the damp and rot and hide the problem – until the glass falls out. Going for a regular 5 mile run is good for you – but not if you are 10 stone (60KG) overweight and have not run in years. A 5 mile run is also not a good idea if you want to be a long-jumper. Right training (methodology) for the right aim. Also, just like keeping healthy, house maintenance or anything that takes effort but works, proponents tend towards extremism – probably as a reaction to the constant {perceived} pig-headedness of critics or the failure of people to just do what now seems so sensible to them {think reformed smokers}. I’ll have to buy Cary and Mike pints to make up for that jibe now, and promise them it was not aimed at them personally…

Sadly, the reality is, Agile does not work 90% of the time it is tried. So, does that mean Agile is actually rubbish? Or at least, not fit for purpose, because many companies are not able to use it? Companies are there to achieve something and the IT systems are part of achieving that something. If Agile cannot aid that IT department then Agile is the wrong way for that department and company.

*sigh* I’ve gone on and on about this and still not got to my own main point, which is this.

- Can we identify reasons for Agile and XP Failing.
- Having identified the Reasons, can we fix them in simple ways?
- Can we create some simple guidelines as to when a project should be more Agile and when it should be more Up-Front design.

I’d love to know people’s opinions on those three points above.

Friday Philosophy – Why doesn’t Agile work? September 16, 2011

Posted by mwidlake in development, Friday Philosophy, Management.
Tags: , ,
13 comments

Why doesn’t Agile Development Methodology seem to work?

I’m going say right here at the start that I like much of what is in Agile, for many, many years I’ve used aspects of Rapid Application Development {which Agile seems to have borrowed extensively from} to great success. However, after my post last week on database design, many of the comments were quite negative about Agile – and I had not even mentioned it in my post!

To nail my flag to the post though, I have not seen an Agile-managed project yet that gave me confidence that Agile itself was really helping to produce a better product, a product more quickly and most certainly not a final system that was going to be easy to maintain. Bring up the topic of Agile with other experienced IT people and I would estimate 90% of the feedback is negative.

That last point about ongoing maintenance of the system is the killer one for me. On the last few projects I have been on where the culture was Agile-fixated I just constantly had this little voice in my head going:

“How is anyone going to know why you did that in six months? You’ve just bolted that onto the side of the design like a kludge and it really is a kludge. When you just said in the standup meeting that we will address that issue ‘later’, is that the same “later” that accounts for the other half-dozen issues that seem to have been forgotten?”.

From what I can determine after the fact, that voice turns out to be reason screaming out against insanity. A major reason Agile fails is that it is implemented in a way that has no consideration for post-implementation.

Agile, as it is often implemented, is all about a headlong rush to get the job done super-quick. Ignore all distractions, work harder, be completely focused and be smarter. It really does seem to be the attitude by those who impose Agile that by being Agile your staff will magically come up with more innovative solutions and will adapt to any change in requirements just because they work under an agile methodology. Go Agile, increase their IQ by 10 points and their work capacity by 25%. Well, it doesn’t work like that. Some people can in fact think on their feet and pull solutions out of thin air, but they can do that irrespective of the methodology. People who are more completer-finishers, who need a while to change direction but boy do they produce good stuff, have you just demoralized and hamstrung them?Agile does not suit the way all people work and to succeed those people it does not suit need to be considered.

The other thing that seems to be a constant theme under Agile is utterly knackered {sorry, UK slang, knackered means tired, worn out and a bit broken} staff. Every scrum is a mad panic to shove it all out of the door and people stop doing other things to cope. Like helping outside the group or keeping an eye on that dodgy process they just adopted as it needed doing. Agile fails when it is used to beat up team. Also, I believe Agile fails when those ‘distractions’ are ignored by everyone and work that does not fall neatly into a scrum is not done.

I suppose it does not help that my role has usually been one that is more Production Support than development and Agile is incompatible with production support. Take the idea of the scrum, where you have x days to analyse, plan, design, unit test and integrate the 6 things you will do in this round. On average I only spend 50% of my time dealing with urgent production issues, so I get allocated several tasks. Guess what, if I end up spending 75% of my time that week on urgent production issues, and urgent production issues have to take priority, I can screw up the scrum all on my own. No, I can’t pass my tasks onto others in the team as (a) they are all fully assigned to their tasks and (b) passing over a task takes extra time. Agile fails when it is used for the wrong teams and work type.

I’ve come to the conclusion that on most projects Agile has some beneficial impact in getting tasks done, as it forces people to justify what they have done each and every day, encourages communication and gives the developers a reason to ignore anything else that could be distracting them as it is not in the scrum. Probably any methodology would help with all of that.

My final issue with Agile is the idiot fanatics. At one customer site I spent a while at, they had an Agile Coach come around to help the team to become more agile. I thought this was a little odd as this team was actually doing a reasonable job with Agile, they had increased productivity and had managed to avoid the worst of the potential negative impacts. This man came along and patronisingly told us we were doing OK, but it was hard for us to raise our game like this, we just needed help to see the core values of Agile and, once we did, once we really believed in it, productivity would go up 500% {That is a direct quote, he actually said “productivity will go up by 500%”}. He was sparkly-eyed and animated and full of the granite confidence of the seriously self-deluded. I think he managed to put back the benefits of Agile by 50%, such was the level of “inspiration” he gave us. Agile fails when it is implemented like a religion. It’s just a methodolgy guys.

I find it all quite depressing as I strongly suspect that, if you had a good team in a positive environment, doing a focused job, Agile could reap great rewards. I’m assured by some of my friends that this is the case. {update – it took my good friend Mike less than an hour to chime in with a comment. I think I hit a nerve}.

Friday Philosophy – Tainted by the Team August 26, 2011

Posted by mwidlake in development, Friday Philosophy, humour, Management, rant.
Tags: , , , ,
3 comments

A while ago whilst working on one project, a colleague came back to his desk next to mine and exclaimed “I hate working with that team! – they are so bad that it makes everyone who works with them look incompetent!”

Now there is often an argument to be made that working with people who are not good at their job can be great for you, as you always looks good in comparison {it’s like the old adage about hanging around with someone less attractive than you – but I’ve never found anyone I can do that with…}. It is to an extent true of course, and though it can seem a negative attitude, it is also an opportunity to teach these people and help them improve, so everyone potentially is a winner. I actually enjoy working with people who are clueless, so long as they will accept the clues. You leave them in a better state than when you joined them.

However, my friend was in the situation where the team he was dealing with was so lacking in the skills required that if you provided them with code that worked as specified, which passed back the values stated in the correct format derived from the database with the right logic… their application code would still fall over with exceptions – because it was written to a very, very “strict” interpretation of the spec.

In one example, the specification for a module included a “screen shot” showing 3 detail items being displayed for the parent object. So the application team had written code to accept only up to 3 detail items. Any more and it would crash. Not error, crash. The other part of the application, which the same people in the application team had also written, would let you create as many detail items for the parent as you liked. The data model stated there could be many more than 3 detail items. I suppose you could argue that the specification for the module failed to state “allow more than three items” – but there was a gap in the screen to allow more data, there was the data model and there was the wider concept of the application. In a second example, the same PL/SQL package was used to populate a screen in several modes. Depending on the mode, certain fields were populated or not. The application however would fail if the variables for these unused fields were null. Or it would fail if they were populated. The decision for each one depended on the day that bit of the module had been written, it would seem. *sigh*

The situation was made worse by the team manager being a skilled political animal, who would always try to shift any blame to any and all other teams as his first reaction. In the above examples he tried to immediately lay the blame with my colleague and then with the specification, but my colleague had managed to interpret the spec fine (he did the outrageous thing of asking questions if he was not sure or checked the data model). Further, this manager did not seem to like his people asking us questions, as he felt it would make it look like they did not know what they were doing. Oddly enough they did NOT know what they were doing. Anyway, as a consequence of the manager’s hostile attitude, the opportunity to actually teach the poor staff was strictly limited.

That was really the root of the problem, the manager. It was not the fault of the team members that they could not do the job – they had not had proper training, were unpracticed with the skills, siloed into their team, not encouraged to think beyond the single task in front of them and there was no one available to show them any better. The issue was that they were being made to do work they were not able to do. The problem, to my mind, was with the manager and with the culture of that part of the organisation that did not deal with that manager. He obviously did not believe that rule one of a good manager is to look after the best interests of your team. It was to protect his own backside.

But the bottom line was that this team was so bad that anything they were involved in was a disaster and no one wants to be part of a disaster. If you worked with them, you were part of the disaster. So we took the pragmatic approach. When they had the spec wrong, if we would alter our code to cope, we would alter our code. And document that. It gave us a lot of work and we ended up having a lot of “bugs” allocated to our team. But it got the app out almost on time. On-going maintencance could be a bit of an issue but we did what we could on our side to spell out the odditites.

I still know my friend from above and he still can’t talk about it in the pub without getting really quite agitated :-)

Friday Philosophy – The Secret to Being a Good IT Manager June 3, 2011

Posted by mwidlake in Friday Philosophy, humour, Management.
Tags: , ,
10 comments

If you go into a book shop there will probably be a section on business and, if there is, there will almost certainly be a load of books on how to be a manager. Shelves and shelves of them. There is also a large and vibrant market in selling courses on management and aspects of management. I’ve been on a couple of such course and, if you can manage to be open minded whilst keeping a cynical edge, I think they can be useful.

However, I think I most of them are missing the key points and that if you can but hold on to the following extensive list of guiding principles you will be a good IT manager. Maybe even an excellent one :-):

  1. Your top priority, at all times, is to see to the best interests of your people.
  2. Whatever you develop, be it code, databases, network, a team of support staff – User Acceptance is paramount.
  3. You must find ways to deal with other teams and your own management hierarchy in such a way as to be allowed to do (1) and (2).
  4. That’s it.
  5. OK, if pushed, I’d say Never Lie. Maybe that’s just personal though, it’s because I don’t have the memory, audacity or swiftness of mind to pull it off. By not lying I don’t have to try and construct what I said to who and why.

I’m sure people could cite some other hard rules like “you must be within budget” or “you need to get buy-in to your vision” but I don’t agree. Budgets can be negotiated and the difference between those deemed visionaries and those deemed fantasists seems to be to me down to success and luck. Luck is luck and for success I refer you to points 1 through 5.

OK, maybe a final rule is:

  • Never ask for or aim for something that is not realistic.

So, I am now able to develop my team and my application and not expect to be able to spend half the company profit on the fastest box out there, as it is not realistic.

There are a shed load of other things that I think are important to helping you be a good manager, you know, techniques and methods for improving things, but nothing else that is key.

And it’s such a simple, small list even I can aim for it.

The shame of it is that I don’t think it’s enough to be developed into a book or a course so I can’t sell the idea. That and I’ve gone and given it away in this blog. Also, though I feel I can give points 1,2 and 5 a good shot, point 3 is way beyond me…possibly because of point 5… So I am not a great manager.

I’m going to hide behind this stout wall now, with my hard hat on, and wait to be told how naive I am…

Update – A couple of weeks later, Kellyn on her DBA Kevlar blog put similar sentiments to looking after your guys, more from the employee’s perspective and far better covered

Why given so many of us feel this way and want things to be this way…are they not?

Team Work & The Science of Slacking July 23, 2010

Posted by mwidlake in Friday Philosophy, Management, Perceptions.
Tags: , , ,
add a comment

We all know that working in a team is more efficient than working on your own (and I did say a week or two back how I was enjoying the rare privilege of working in a team of performance guys). Many of us also know about team dynamics and creating a balanced team of ideas people, completer-finishers, implementers, strategists and so forth. Those of use who have been exposed to training courses or books on team management know all these good things about teams and how we are supposed to get the most out of them.

How many of us, though, have been introduced to the work of the French Agronomist Max Ringelmann and the aspect of teams named after him, the Ringelmann Effect? In summary the Ringelmann Effect proposses that people in teams try less hard than they do when working alone. Especially if they think no one is watching them.

Back at the start of the 20th century Ringelmann tested out his ideas using a tug-of-war experiment. He would get people to pull on a rope as hard as they could and record their efforts using a strain gauge. Then he would get them to pull on the rope as part of a team, from 2 to 8 people. As soon as people were part of a team, they pulled less hard. With two people in the team, each pulled 93% as hard as on their own, with three people this dropped down to 85% and with 4 it was just 77%. By the time there were 8 people in the team, effort was down to 50%.

This idea of shirking work more and more as the team increased in size became established in modern psychology and was given Mr Ringelmann’s name. Psychologists explain that when someone is part of a group effort then the outcome is not solely down to the individual and, as such, is not totally in their control. This acts as a demotivating factor and the person tries that little bit less hard. The larger the team, the greater the demotivation and the more significant the drop in effort. Ringelmann found that effort was down to 50% in a team of 8 so how bad can the impact of the team be? I think most of us have at least witnessed, and quite possibly been in, the position of feeling like just a cog in a massive corporate team machine. Thoroughly demotivating (though, of course, we all of us still tried as hard as we could, didn’t we?).

The effect is also know under the far more entertaining title of Social Loafing.

Monsieur Ringelmann was far kinder at the time and pointed out that these chaps pulling on the rope could well have been suffering from a lack of synergy. They had not been trained together to pull as a team so that could account for the drop in effort, they were not synchronising their effort.

However, in the 1970′s Alan Ingham in Washington University revisited Ringelmanns work and he was far sneekier. Sorry, he was a more rigorous scientist. He used stooges in his team of rope-pullers, blindfolds and putting the one poor person pulling for real at the front of the team pulling the rope. Thus he could record the effort of the individual. Ingham found that there was indeed a drop in efficiency due to the team not pulling as one. But sadly, this was not the main factor. It remained that the drop in effort was mostly down to the perceived size of the rest of the team. The bottom line was proven to be the human capacity to try less hard when part of a team and that the drop in effort was directly proportional to the size of the team.

We are of course not immune to this effect in the IT world and someone has even gone to the effort of checking that out, James Suleiman and Richard T Watson.

It seems the ways to reduce this problem are:-

  • Don’t give people boring jobs.
  • Don’t give the same job to several people and let them know they all have the same job.
  • Ask people how they are getting on and give them mini-goals along the way.
  • Atually reward them for success. Like saying “thank you” and NOT giving them yet another boring, hard job to do as they did the last one so well.

I think it is also a good argument for keeping teams small {I personally think 5 or 6 people is ideal} and split up large projects such that a single team can cope. Then give tasks to individuals or pairs of people.

If you like this sort of thing you might want to check out one of my first blog post (though it is more an angry rant than a true discussion ofthe topic) which was on the Dunning-Kruger effect, where some people are unaware of their own limitations – though I did not know it was called the Dunning-Kruger effect until others told me, which only goes to show that maybe I am not aware of my own limits… Read the comments or click through to the links from there to get a better description of some people’s inability to guage their own inabilities.

More Memory Meanderings – IOPS and Form Factors July 19, 2010

Posted by mwidlake in Architecture, Management, performance.
Tags: ,
8 comments

I had a few comments when I posted on solid state memory last week and I also had a couple of interesting email discussions with people.

I seriously failed to make much of one of the key advantages of solid-state storage over disk storage, which is the far greater capacity of Input/output operations per second (IOPS), which was picked up by Neil Chandler. Like many people, I have had discussions with the storage guys about why I think the storage is terribly slow and they think it is fast. They look at the total throughput from the storage to the server and tell me it is fine. It is not great ,they say, but it is {let’s say for this example} passing 440MB a second over to the server. That is respectable and I should stop complaining.

The problem is, they are just looking at throughput, which seems to be the main metric they are concerned about after acreage. This is probably not really their fault, it is the way the vendors approach things too. However, my database is just concerned in creating, fetching, and altering records and it does it as input/output operations. Let us say a disk can manage 80 IOPS per second (which allows an average 12.5 ms to both seek to the record and also read the data. Even many modern 7,200 rpm discs struggle to average less than 12ms seek time). We have 130 disks in this example storage array and there is no overhead from any sort of raid or any bottleneck in passing the data back to the server. {This is of course utterly unbelievable, but if i have been a little harsh not stating the discs can manage 8ms seek time, ignoring the raid/hba/network cost covers that}. Each disc is a “small” one of 500GB. They bought cheap disk to give us as many MB/£ as they could {10,000 and 15,0000 rpm disks will manage 120 and 160 IOPS per second but cost more per MB}.

Four sessions on my theoretical database are doing full table scans, 1MB of data per IO {Oracle’s usual max on 10.2}, Each session receiving 100MB of data a second, so 400MB in total. 5 discs {5*80 IOPS*1MB} could supply that level of IOPS. It is a perfect database world and there are no blocks in the cache already for these scans to interrupt the multi-block reads.

However, my system is primarily an OLTP system and the other IO is records being read via index lookups and single block reads or writes.

Each IOP reads the minimum for the database, which is a block. A block is 4k. Oracle can’t read a bit of a block.

Thus the 40MB of other data being transferred from (or to) the storage is single block reads of 4k. 10,000 of them. I will need 10,000/80 disks to support that level of IO. That is 125 discs, running flat out.

So, I am using all my 130 discs and 96% of them are serving 40MB of requests and 4% are serving 400MB of requests. As you can see, as an OLTP database I do not care about acreage or throughput. I want IOPS. I need all those spindles to give me the IOPS I need.

What does the 40MB of requests actually equate to? Let us say our indexes are small and efficient and have a height of 3 (b-level of 2), so root node, one level of branch nodes and then the leaf nodes. To get a row you need to read the root node, branch node, lead node and then the table block. 4 IOs. So those 10,000 IOPS are allowing us to read or write 10,000/4 records a second or 2,500 records.
You can read 2,500 records a second.

Sounds a lot? Well, let us say you are pulling up customer records onto a screen and the main page pulls data from 3 main tables (customer, address, account_summary) and translates 6 fields via lookups. I’ll be kind and say the lookups are tiny and oracle just reads the block or blocks of the table with one IO. So that is 9IOs for the customer screen, so if our 40MB OLTP IO was all for looking up customers then you could show just under 280 customers a second, across all users of your database. If you want to pull up the first screen of the orders summary, each screen record derived from 2 underlying main tables and again half a dozen lookups, but now with 10 records per summary page – that is 80 IOs for the page. Looking at a customer and their order summary you are down to under thirty a second across your whole organisation and doing nothing else.

You get the idea. 2,500 IOPS per second is tiny. Especially as those 130 500GB disks give you 65TB of space to host your database on. Yes, it is potentially a big database.

The only way any of this works is due to the buffer cache. If you have a very healthy buffer cache hit ratio of 99% then you can see that your 2500 records of physical IO coming in and out of the storage sub-system is actually supporting 250,000 logical-and-physical IOPS. {And in reality, many sites not buffer at the application layer too}.

Using Solid State Storage would potentially give you a huge boost in performance for your OLTP system, even if the new technology was used to simply replicate disk storage.

I think you can tell that storage vendors are very aware of this issue as seek time and IOPS is not metrics that tend to jump out of the literature for disk storage. In fact, often it is not mentioned at all. I have just been looking at some modern sales literature and white papers on storage from a couple of vendors and they do not even mention IOPS – but they happily quote acreage and maximum transfer rates. That is, until you get to information on Solid State Discs. NOw, because the vendor can say good things bout the situation then the information is there. On one HP white paper the figures given are:

				Modern super-fast		Top-end 
				SAS disk drive Top-end 	Solid State Disk
Sustained write     	150MB/s			180MB/s
Sustained read			90MB/s			180MB/s
Random write			285				5,000+
Random read				340				20,000+ 

More and more these days, as a DBA you do not need or want to state your storage requirements in terms of acreage or maximum throughput, you will get those for free, so long as you state your IOPS requirements. Just say “I need 5000 IOPS a second” and let the storage expert find the cheapest, smallest disks they can to provide it. You will have TBs of space.

With solid-state storage you would not need to over-specify storage acreage to get the IOPS, and this is why I said last week that you do not need solid state storage to match the capacity of current disks for this storage to take over. We would be back to the old situation where you buy so many cheap, small units to get the volume, IOPS are almost an accidental by-product. With 1GB discs you were always getting a bulk-buy discount :-)

I said that SSD would boost performance even if you used the technology to replicate the current disk storage. By this I mean that you get a chunk of solid-state disk with a SATA or SAS interface in a 3.5 inch format block and plug it in where a physical disk was plugged in, still sending chunks of 4k or 8k over the network to the Block Buffer Cache. But does Oracle want to stick with the current block paradigm for requesting information and holding data in the block buffer cache? After all, why pass over and hold in memory a block of data when all the user wanted was a specific record? It might be better to hold specific records. I suspect that Oracle will stick with the block-based structure for a while yet as it is so established and key to the kernel, but I would not be at all surprised if something is being developed with exadata in mind where data sets/records are buffered and this could be used for data coming from solid state memory. A second cache where, if using exadata or solid-state memory, holding single records. {I might come back to this in a later blog, this one is already getting bloated}.

This leads on to the physical side of solid-state discs. They currently conform to the 3.5” or 2.5” hard disc form factor but there is no need for them to do so. One friend commented that, with USB memory sticks, you could stick a female port on the back of a memory stick and a joint and you could just daisy-chain the USB sticks into each other, as a long snake. And then decorate your desk with them. Your storage could be looped around the ceiling as bunting. Being serious, though, with solid state storage then you could have racks or rows of chips anywhere in the server box. In something like a laptop the storage could be an array 2mm high across the bottom the chasis. For the server room you could have a 1u “server” and inside it a forest of chips mounted vertically, like row after row of teeth, with a simple fan at front and back to cool the teeth (if needed at all). And, as I said last time, with the solid state being so much smaller and no need to keep to the old hard disk format, you could squeeze a hell of a lot of storage into a standard server box.

If you pulled the storage locally into your server, you would be back to the world of localised storage, but then LANs and WANs are so much faster now that if you had 10TB of storage local to your server, you could probably share it with other machines in the network relatively easily and yet have it available to the local server with as many and as fat a set of internal interfaces as you could get your provider to manage.

I’m going to, at long last, wrap up this current instalment on my thoughts with a business one. I am convinced that soon solid-state storage is going to be so far superior a proposition to traditional disks that demand will explode. And so it won’t get cheaper. I’m wondering if manufacturers will hit a point where they can sell as much as they can easily make and so hold the price higher. After all, what was the argument for Compact Discs to cost twice as much to produce as old cassette tapes, even when they had been available for 5 years? What you can get away with charging for it.

Friday Philisophy – To Manage or to Not Manage March 26, 2010

Posted by mwidlake in Friday Philosophy, Management, Uncategorized.
Tags: ,
6 comments

Recently a friend of mine Graham Oaks blogged about his decision to step back from management and return to the Technical Coal Face.

I made a similar decision 3 or 4 years back, so I have a lot of empathy for his position and his decision. I found that to do the job of a manager takes up a lot more time, effort, patience and emotional effort than I had realised. Team leading is bad enough, having to coordinate the efforts of a half dozen people and sorting out the myriad issued they throw your way. Being in charge of multiple teams, responsible for strategy, dealing with staff development and moral, being a buffer against HR and having to deal with the politics created by people who WANT to be managers and wield power is more than a full-time job. Trying to hold onto a technical element as well, I found I could only manage it by doing the technical job as a “hobby”, in my own time. It was just too much to keep going year after year.

I had to chose. Give up the technical to give me enough personal resource to remain a manager and get better at it, or stop being a manager and start re-gaining my technical skills. I chose the latter.

Since I made my decision 3 years ago, I have met several people who have made the same conscious decision to step away from management and return to a more technical role. You may stand to earn more as a manager {which is something I objected to before being a manager and I still object to having been one – it should be possible to earn the same doing either} but for some of us it is not enough to make losing the hands-on work a sacrifice worth making.

One of the points Graham makes in his blog is that his spell as a manager has given him an appreciation of the challenges of management and the particular hells and stresses of the role. I think this is something that people who have never been managers have trouble really understanding.

I was working with a guy a couple of years ago and he was telling me how much of “a Moron” his boss was. In fact, he felt his current boss was even more of a moron than his previous boss. He then confessed that all of his bosses had been morons. “What, every single one of them?” I asked. Yes, absolutely all of them. That struck me as incredibly unfortunate, that every single one of these managers (and he’d had a lot as he moved between teams and positions on a regular basis), most of whom had come up through the technical ranks, were all Morons. I pointed out this unfortunate coincidence and wondered if there might actually be a common factor with all of these managers. He told me there was; They were all Morons.

He himself had never been a manager. He said he was too smart. Not smart enough to get what I was hinting at with the common factor suggestion though.

Obviously, some managers are poor at what they do; there are poor people in every job. But something I took away from my time being a manager is a lack of empathy for anyone saying all managers are a waste of time when they have never done the job themselves.

After all, I doubt there is any job where just doing it means you are an idiot.

Except Sys Admins – They are all idiots :-) (ducks behind server).

Advert for the Management and Infrastructure SIG March 24, 2010

Posted by mwidlake in Management, Meeting notes.
Tags: , ,
4 comments

I’m a bit late doing this (life is just too busy at the moment) but I want to mention the next Management and Infrastructure Special Interest Group meeting of the UKOUG next Week. Tuesday 30th, being held in Oracle’s London City office.

I get asked by people what exactly the MI SIG is? {Honest, I do, I got asked twice this month alone!}. Is it a management meeting or is it another one of the technical SIGs, like the UNIX, RDBMS and RAC/HA SIGs? I’ve struggled to come up with a single line to sum it up. Other than to say “Both”.

It might be easier to sum up the target audience. The MI SIG is for technical people who need to deal with Oracle as a component of a large IT environment. Most of the audience could knock up a PL/SQL script to create a new set of tablespaces each month, would be able to instal Oracle {if given a couple of days and the manuals to peek at} and could explain two-phase commit. Maybe.
But what they have to deal with in their working lives are things like using Grid Control to manage 500 instances, understand what options are there for providing disaster recovery {if not the exact commands to eg set up physical standby or active/passive RAC}, knowing enough about storage options to make a sensible decision on which is best for each type of Oracle system they have. So it is a technical SIG, but covering general principles and, well, Infrastructure.

And the Management? Well, when the SIG started this bit was really interesting to me. When you have a lot of IT going on, especially in large organisations, the people looking after Oracle are not the people looking after Networks, or Storage, or Backups or half a dozen other things. And you probably have a team of people doing all that Oracle stuff with/for you. So you have to hire staff and keep ‘em happy and deal with teams who you have no power over but you need them to do stuff for you. And that Management part can be a lot harder than the technology, especially if you never planned on being a manager but just woke up one day with that monkey on your back.

So with the technical aspects of Large IT Infrastructure comes the management component too. The SIG is there for that audience.

I chair this SIG, so I am more than a little bit biased, but I think it is a good line-up of talks for this up-coming meeting. We have two talks on using OEM/Grid Control, one around using it for deploying clusters, one about how you go about integrating it with the likes of LDAP, Kerbros and using the Custom Metrics, ie plugging it into the wider infrastructure.

We also have a presentation on the latest/greatest Exadata2, from some Oracle friends.

To wrap up the technical talks I am going to try and explain some of the guiding principles for gathering statistics for you oracle databases. Not the details of DBMS_STATS command syntax, but why you need good stats, how you get them and the issues we all seem to end up facing with it.

Balancing the techical side is a talk on Birkman and understanding teams and people.

So, you can see it is a line-up matching the diversity of the SIG’s purpose.

As I said earlier, I initially was very interested in the management side of the SIG and I worried I would be pretty lonely in that opinion. For various reasons, those of us on the technical side tend not to have much time for those “soft skills” we associate with management theory. However, when I took over the SIG over a year ago, I asked the audience if they would want some talks on hiring staff, dealing with people, motivation… Over 60% of the audience said “YES!”. Quite loudly. About 30% said “OK, so long as we get technical stuff as well”. 6% said “over my dead body”.

I think the reason so many wanted the management side as well is, whether we like it or have an affinity for it or not, it is part of the job. And so we need to be able to do it. Personally, I quite like the human side of IT, but my wife tells me I am strange.

If your organisation has UKOUG membership it is free to come along to the SIG (one person per membership, excluding Bronze membership) Anyone can come along for £80. You would be very welcome and I am sure you will learn new stuff. Don’t let the fact that we retire to a pub afterwards where the chair buys a round sway your decision to come along at all.

Follow

Get every new post delivered to your Inbox.

Join 156 other followers